Metrorrey Line 4 (Monorail)
Under Construction7.62 km (4.7 mi) elevated monorail running west along Avenida Constitución from Hospital de Ginecología in downtown Monterrey to Pablo González, where it will meet the planned federal passenger train, with seven stations in the 2025 plan. A planned extension to Santa Catarina was dropped in 2025. The state reported works on Lines 4 and 6 at 96% (viaduct 95.6%, stations 56.7%) in September 2026; passenger service is targeted for 2027.
Alignment Map
Map tiles © OpenStreetMap contributors. Alignment is approximate.
Alignment
Line 4 is an elevated straddle-beam monorail that starts at Hospital de Ginecología on Avenida Constitución at Félix U. Gómez, where it shares a station with Line 6. It runs west along Avenida Constitución past Barrio Antiguo, downtown Monterrey, and the Obispado area, then follows part of Avenida San Jerónimo to Pablo González. The state plans for Pablo González to connect with the federal Monterrey–Nuevo Laredo passenger train. The February 2025 plan listed seven stations: Hospital de Ginecología, Palacio Municipal, Pabellón, ISSSTE, Obispado, San Jerónimo, and Pablo González. State and press reports since then also refer to stations at Juárez and Serafín Peña, so the final station list is not settled.
Lines 4 and 6 form one monorail network, with 21 stations across Line 4, Line 6, and Line 6’s airport branch. A Mota-Engil México and CRRC Hong Kong consortium is building the lines under a single contract, with CRRC supplying the trains. The state government’s Secretaría de Movilidad y Planeación Urbana manages construction, and Metrorrey will operate the line.
Updates
2026-11 — Governor inspects Line 4 stations; service targeted for 2027
On November 2, Governor Samuel García toured the Ginecología, Palacio, and Juárez stations on Avenida Constitución, along with related work at Puente Nuevo and Torre Rise. Metrorrey’s director said the state aims to start passenger service on Lines 4 and 6 and the airport branch during 2027, before the current administration ends.
2026-09 — Viaduct for Lines 4 and 6 nearly complete
The state reported 96% overall progress on Lines 4 and 6, with the viaduct at 95.57% and stations at 56.65%. The last beams were being placed, including at the Avenida Gonzalitos crossing, where officials said the work would be done at night and roads would not be closed.
2026-01 — Power supply for the western branch confirmed
During a site visit, Metrorrey’s director said the Y Griega substation, which will also house the central control post, will power both the branch toward the airport and the branch toward Pablo González, the Line 4 terminal that will connect with the Monterrey–Nuevo Laredo train. He said civil works there were practically finished and electromechanical equipment was 70% complete.
2025-12 — Line 4 reaches 75%
The state put Line 4 at 75% complete and Lines 4 and 6 together at 78%. Work included foundations, columns, station platforms, the Avenida Juárez interchange, and Serafín Peña station.
2025-02 — Santa Catarina extension dropped
Governor García said the federally funded extension of Line 4 to Santa Catarina had been cancelled at the federal government’s request, because the planned federal passenger train will serve that corridor. The revised line ends at Pablo González, at 7.62 km with seven stations.
2023-04 — Construction begins
Construction began on April 11, 2023, on a line of just over 7 km from the IMSS Hospital de Ginecología to Pablo A. González, at the edge of Monterrey and San Pedro Garza García.
2022-09 — Contract awarded for Lines 4, 5, and 6
After an international tender launched in April 2022, the state awarded the contract for Lines 4, 5, and 6 to Mota-Engil México and CRRC Hong Kong on September 23, 2022. The bid was about MX$25.86B plus VAT with all three lines elevated. The tender set an August 2027 deadline for construction.
References
- Descarta Estado cierres viales en Gonzalitos por obras de L4 del Metro (CP/1262/2026)Gobierno del Estado de Nuevo León · Sep 7, 2026
- Estamos construyendo un Metro del futuro e incluyente: Samuel García (CP/0039/2026)Gobierno del Estado de Nuevo León · Jan 13, 2026
- Líneas 4 y 6 del Metro avanzan con paso firme: 78% de progreso en la obra (CP/1753/2025)Gobierno del Estado de Nuevo León · Dec 18, 2025
- Metrorrey Line 4Wikipedia
- Monorriel de la Línea 6 ya llegó a Apodaca, en recorrido de pruebaPublimetro · Nov 4, 2026
- Samuel García supervisa la estación Churubusco y anuncia su inauguración este mesMundo Ejecutivo · Nov 2, 2026
- ¿Hasta dónde llegará la Línea 4 del Metro de Monterrey? Aquí las estaciones completasMilenio · Feb 26, 2025
- El 11 de abril inicia la construcción de la Línea 4 del Metro, anuncia Gobierno de NLPublimetro · Apr 5, 2023