Brightline Orlando–Tampa Extension
PlanningProposed ~85–90-mile extension of Brightline's Miami–Orlando intercity service from Orlando International Airport to Tampa. It would share a new Sunshine Corridor track with SunRail along SR 528 to the Convention Center, then run in the median FDOT has preserved along I-4. Stations beyond the Convention Center are undecided. With no cost estimate or schedule, the project's prospects became more uncertain after Brightline's parent companies filed for Chapter 11 in September 2026.
Alignment Map
Map tiles © OpenStreetMap contributors. Alignment is approximate.
Alignment
The extension would continue Brightline’s Miami–Orlando trains west from its Orlando International Airport station. Leaving the airport, it would follow existing Orlando Utilities Commission tracks past Brightline’s maintenance facility to the SunRail line north of Meadow Woods. It would then take new grade-separated track along State Road 528, shared with SunRail as part of the proposed Sunshine Corridor, to a station at the Orange County Convention Center on International Drive. From there it would turn southwest into the median of Interstate 4, which the Florida Department of Transportation (FDOT) has kept clear for a two-track rail line since the high-speed rail plans of the 1990s, and run to Tampa. That sealed, grade-separated corridor could take trains at up to 125 mph. Brightline has said the airport–downtown Tampa trip would take about an hour.
Several stations are undecided. Brightline’s 2020 deal for a station at Disney Springs fell apart in 2022 when the route moved north to SR 528. Brightline then proposed a station near Disney Springs but off Disney property, and no Disney-area or EPCOT-area stop has been confirmed since. Earlier plans showed a stop in the Lakeland area. In Tampa, a 2020 agreement pointed to Ybor City, and a 2025 Hillsborough TPO study found strongest support for downtown, Ybor City, or Channelside, but no site has been chosen.
The 2018 plan put the route at 88 miles and $1.7 billion. Brightline has not published a current cost. Construction depends on public money for the shared Sunshine Corridor, which FDOT estimated in 2024 at about $4 billion from the airport to I-4.
Updates
2026-09 — Brightline’s parent companies file for Chapter 11
Seventeen Brightline Florida parent companies, holding about $2.5 billion of holding-company debt, filed for Chapter 11 in New Jersey on September 24 under a restructuring deal that brings $490 million in new long-term financing. The operating railroad did not file and trains kept running. The Tampa rights sit with an affiliate outside the bankruptcy but are pledged as collateral for bonds, and that affiliate missed a third straight interest payment on $1.2 billion of bonds in July. Hillsborough’s TPO said construction could not start until FDOT finishes I-4 roadwork and that another rail company could take up the project.
2025-07 — Brightline seeks up to $400 million in bonds; Tampa surveys station sites
Brightline asked the Florida Development Finance Corporation to issue up to $400 million in private activity bonds, partly to advance design and planning for Tampa. On July 15 Tampa’s city board voted unanimously to let the bond process continue. Trains reported that no total cost had been estimated. A Hillsborough County commissioner said Tampa service was “about a decade” away. More than 11,000 people answered the TPO’s station survey.
2024-04 — FDOT prices the airport-to-I-4 link at $4 billion
An FDOT study put the cost of the shared rail link from Orlando International Airport to the I-4 corridor at $4 billion. A cheaper $400 million option connecting only SunRail to the airport would block Brightline’s access to the I-4 median. FDOT expected the cost to be split among state, local, private, and federal sources.
2022-06 — Disney Springs dropped as the route moves to SR 528
After Universal Orlando and local leaders pushed for a different alignment, Brightline replaced its SR 417 route, which had a Disney Springs station, with the Sunshine Corridor plan. The new route along SR 528 and International Drive would serve the Convention Center and a station near Disney Springs on land Disney does not own. Brightline put the cost of the new Orlando routing at $2.4 billion, $1 billion more than the original.
2020-11 — Disney Springs station agreed
Brightline and Walt Disney World announced a station at Disney Springs, with the segment from the airport along SR 417 projected at $1 billion. In September 2020 Brightline had signed a memorandum of understanding with a developer for a Tampa terminal in Ybor City.
2018-11 — Brightline cleared to negotiate for the I-4 median
FDOT allowed Brightline, the only bidder, to negotiate a lease of the I-4 median. The 88-mile plan was then estimated at $1.7 billion, with stations in Orlando, the Celebration and Lakeland areas, and Tampa.
References
- What We Learned from 11,000 Brightline Surveys (Yes, Really!)Hillsborough Transportation Planning Organization (Plan Hillsborough) · Jul 22, 2025
- BrightlineWikipedia
- Brightline Florida parent companies seek to restructure $2.5 billion in debt through Chapter 11 bankruptcyMass Transit · Sep 29, 2026
- Brightline is filing for Ch. 11 bankruptcy protection. What does that mean for Tampa?Tampa Bay Times (via Yahoo Finance) · Sep 25, 2026
- Brightline seeks private activity bonds for Tampa extension: AnalysisTrains · Jul 14, 2025
- Brightline proposes plan to issue up to $400M in bonds to pay for Tampa extension: FDFC noticeFOX 13 Tampa Bay · Jul 11, 2025
- SunRail airport connection to Orlando attractions, Brightline Tampa route has $4 billion price tagTrains · Apr 26, 2024
- Disney Springs no longer a stop on Brightline's Miami to Tampa routeWKMG News 6 (ClickOrlando) · Jun 28, 2022
- Brightline Gets OK For I-4 Median, But What's Next?WUSF · Nov 29, 2018