Projects in Alberta
Canada · 2 projects
| Project | Agency | Mode | Status | Alignment | Last Updated |
|---|---|---|---|---|---|
| Green Line LRT (Phase 1) | City of Calgary | light rail | Under Construction | 17 km first phase of Calgary's Green Line LRT, from Shepard in the southeast to a new at-grade station on 10 Avenue near 2 Street SW, with 11 stations. The 16 km SE Segment has been under construction since June 2025; council approved a surface route for the downtown section in September 2026, and opening is targeted for 2031. | Nov 13, 2026 |
| Valley Line West LRT | City of Edmonton | light rail | Under Construction | 14 km low-floor LRT extension of the Valley Line from downtown Edmonton (102 Street) west to Lewis Farms, with 14 street-level stops and two elevated stations. Construction was 64.4% complete at the end of March 2026 and is expected to finish in 2028; an opening date will be set after testing. | Nov 13, 2026 |