Eglinton Crosstown West Extension
Under Construction9.2 km (5.7 mi) westward extension of Line 5 Eglinton from Mount Dennis to Renforth, with seven new stations: four underground, two elevated over the Humber River valley, and one in an open trench. All tunnelling was finished by August 2026, and station construction is under way. A further 4.7 km link to Pearson Airport is still only being studied.
Alignment Map
Map tiles © OpenStreetMap contributors. Alignment is approximate.
Alignment
The extension continues Line 5 Eglinton 9.2 km west from Mount Dennis station, its current western terminus at Weston Road, to Renforth Drive. From Mount Dennis, trains run through a short tunnel and come to the surface along the north side of Eglinton Avenue West east of Jane Street. They then climb onto a 1.5 km elevated guideway, built in 35 spans, that crosses the Humber River and its floodplain. That section has two elevated stations, Jane and Scarlett.
West of Scarlett Road the line enters a 6.3 km twin-bore tunnel under Eglinton Avenue, with underground stations at Royal York, Islington, Kipling and Martin Grove. It ends at Renforth, an open-trench station beside the eastern end of the Mississauga Transitway, near the Toronto–Mississauga boundary. The extension will connect with the UP Express, GO Transit, TTC and MiWay. Together with the main Crosstown line it will form a continuous rapid transit route from Scarborough to Mississauga. Wikipedia lists a forecast of 96,700 daily riders.
Metrolinx and the Greater Toronto Airports Authority are studying a further extension of up to 4.7 km, with as many as three more stations, from Renforth north to Pearson International Airport. That link is not funded or scheduled. The first section of Line 5 Eglinton, from Mount Dennis to Kennedy, opened in early 2026.
Updates
2026-08 — Tunnelling complete
Ontario and the federal government marked the end of tunnelling on August 11. The final piece was a pair of parallel tunnels, each about 500 m long, between Mount Dennis station and Jane Street. Strabag dug them with sequential excavation rather than tunnel boring machines. The federal government is contributing about C$1.87B to the extension. Metrolinx’s timeline shows station excavation starting in July 2026.
2026-05 — First span of the Humber River guideway in place
Metrolinx finished the first of 35 bridge spans on the 1.5 km elevated guideway over the Humber River valley. blogTO reported that the extension is scheduled for completion in 2031, although Metrolinx has not published a firm opening date.
2025-08 — Partner chosen for stations, rail and systems
Infrastructure Ontario and Metrolinx signed a development and master construction agreement with Trillium Rail Partners (Amico, Alberici and Acciona, with designer WSP). The progressive design-build contract covers the seven stations, track and systems, and changes at Mount Dennis station. During its development phase the team can start early works while design, risk and pricing are settled.
2025-02 — Eastern tunnels started
Strabag, which won the Jane-to-Mount Dennis tunnel contract in February 2024, began construction. Aecon had won the contract for the elevated Humber River guideway in December 2023.
2024-06 — Western tunnels complete
The tunnel boring machines Renny and Rexy finished the twin 6.3 km tunnels between Renforth and Scarlett Road, about three weeks apart. The contractor was West End Connectors (Dragados, Aecon and Ghella), and boring had started in April 2022.
2021-05 — First tunnel contract and federal funding
Metrolinx awarded the Renforth–Scarlett tunnel contract to West End Connectors on May 20, 2021, and broke ground at the Renforth launch shaft that July. Ottawa committed to fund 40% of four GTA rapid transit projects, listing the West Extension at an estimated C$4.7B. That figure came from the 2020 business case for a grade-separated line, after earlier plans for a cheaper surface LRT along Eglinton were dropped.
References
- Eglinton Crosstown West ExtensionMetrolinx
- Agreement signed for Eglinton Crosstown West Extension Stations, Rail and SystemsInfrastructure Ontario · Aug 28, 2025
- Le gouvernement fédéral souligne l'achèvement du creusement des tunnels du prolongement vers l'ouest de la ligne Eglinton Crosstown (in French)Government of Canada · Aug 11, 2026
- Largest public transit investment in GTA history will create jobs and kickstart the economyGovernment of Canada · May 11, 2021
- Eglinton Crosstown west extensionWikipedia
- Tunnelling complete for Eglinton Crosstown West ExtensionCanadian Association of Railway Suppliers (via ReNew Canada) · Aug 13, 2026
- Toronto's new elevated transit line just crossed a huge milestoneblogTO · May 13, 2026